KDOT Stormwater Culvert Design Specifications
Comprehensive guidelines for designing, installing, and maintaining stormwater culverts that meet KDOT standards while preventing that dreaded "pocket of backwater big enough to stock catfish." Your complete resource from site selection to as-built documentation.
Download Full Specifications
Scope, Purpose & Applicable Standards
This specification covers the design, installation, and maintenance of stormwater culverts for Kansas highways, including new installations, replacements, and upsizing projects. It establishes a consistent approach to ensure culvert systems maintain structural integrity and hydraulic performance throughout their design life.
AASHTO LRFD Bridge Design Specifications
Chapters on hydraulics and structures provide the foundational requirements for load ratings and structural design parameters.
KDOT Standard Specifications
Sections 212 (Culverts) & 212.3 (Materials) outline KDOT-specific requirements that supersede national standards where applicable.
NPDES Stormwater Regulations
Federal environmental requirements for managing runoff and preventing contamination during construction and operation.
Remember the time we tried slipping a 24-inch pipe under I-70 and ended up with a pocket of backwater big enough to stock catfish? Let's not repeat that.
Design Criteria & Project Requirements
10-100yr
Design Storm Range
Culverts must handle runoff from 10-year to 100-year storm events based on roadway classification and criticality.
0.2ft
Min. Freeboard
Minimum hydraulic freeboard required for inlet control to prevent roadway overtopping.
H20-44
Traffic Load Rating
Standard truck live load designation for structural design with appropriate load factors.
All designs must incorporate watershed delineation using USGS maps or HEC-HMS modeling with an allowance for climate change impacts on rainfall intensity. Future roadway widening must be considered in structural calculations, requiring additional load capacity and extension provisions.
Safety factors for both hydraulic performance and structural integrity are non-negotiable. Use KDOT Hydrology Manual for determining watershed characteristics and peak flow calculations.
Hydraulic Analysis Methodology
Critical Flow Computations
Accurate hydraulic analysis forms the backbone of proper culvert design. Select the appropriate method based on watershed size:
  • Unit hydrograph method for watersheds >200 acres
  • Rational method for small catchments <200 acres
  • Peak flow determination using CN method per KDOT Hydrology Manual
All culverts must be analyzed for both inlet and outlet control conditions using Manning's equation and standard discharge tables. For complex profiles or multiple barrel configurations, verify results with HEC-RAS modeling.
Think of Manning's n as the pipe's "toothbrush bristles"—keep 'em clean or you'll choke your flow.
Required Performance Checks
  • Headwater depth vs. allowable roadway clearance
  • Outlet velocity and downstream scour potential
  • Flow capacity throughout culvert length
  • Tailwater conditions and backwater effects
Structural Design & Sizing
1
Load Analysis
Calculate combined effects of dead load, live load (traffic), earth load, and hydraulic uplift forces using LRFD load combinations.
2
Material Selection
Choose appropriate pipe material based on loading conditions, soil chemistry, and design life requirements.
3
Sizing Calculation
Determine minimum diameter based on hydraulic requirements, then verify structural adequacy for the calculated loads.
4
End Treatment Design
Select appropriate headwall, wingwall, or flared end section design from KDOT Standard Drawing 212.
Minimum cover requirements are non-negotiable: maintain at least 1 ft cover for steel pipe and 2 ft for reinforced concrete pipe (RCP) under roadways. All end treatments must include properly sized riprap for energy dissipation, calculated using USGS methodology based on discharge velocity.
I once saw a corrugated steel pipe crushed by a runaway cattle trailer—proof positive that embedment and live‐load checks aren't optional.
Material Selection Criteria
Reinforced Concrete Pipe (RCP)
  • Superior durability (75+ year service life)
  • Excellent crushing strength
  • Heavy - requires crane for installation
  • Higher initial cost, lower lifetime cost
Corrugated Steel Pipe (CSP)
  • Lightweight and flexible
  • Easier installation in remote areas
  • Corrosion concerns in acidic soils
  • 25-50 year service life with proper coating
High-Density Polyethylene (HDPE)
  • Extremely lightweight and corrosion-resistant
  • Rapid installation with fewer joints
  • Floatation risk if not properly anchored
  • Limited load capacity compared to RCP
Material selection must be based on a comprehensive life-cycle cost analysis that considers initial installation costs against maintenance/replacement frequency. Environmental factors including soil pH, abrasion potential, and exposure to de-icing chemicals must be evaluated.
Geotechnical & Bedding Requirements
Critical Soil Investigation
Proper foundation conditions are essential for culvert performance. Conduct Standard Penetration Tests (SPT) to verify soil bearing capacity and evaluate embankment stability before finalizing design.
Groundwater conditions must be thoroughly documented, with dewatering plans developed when the water table is within 2 feet of the proposed invert. Seasonal variation should be considered when scheduling construction.
Settlement Monitoring
Implement plate load testing on prepared subgrade to verify bearing capacity meets design assumptions. Never compromise on compaction verification - differential settlement leads to joint separation and premature failure.

1

2

3

1
Zone 1
Bedding: Granular material with <4" particles, 95% compaction
2
Zone 2
Haunch: Same spec as bedding, placed in 6" lifts, 95% compaction
3
Zone 3
Cover: Native soil or select fill, 95% compaction, placed symmetrically
Step-by-Step Installation Procedures
Pre-construction Meeting
Review plans, identify utilities, establish traffic control plan, and verify all permits are in hand before breaking ground.
Site Preparation & Excavation
Clear vegetation, set diversion dikes, and excavate to bedding elevation plus 2-inch tolerance. Install shoring for trenches deeper than 5 feet.
Bedding & Alignment
Place and compact bedding material, verify with laser-level checks. Set string line for alignment with grade tolerance of ±0.01 ft/ft.
Culvert Placement & Jointing
Install pipe sections from downstream end. Inspect gaskets, apply lubricant, and verify watertight connections at each joint.
Backfill & Compaction
Place backfill in specified zones and lifts, compact to 95% density, alternating sides to prevent pipe movement. Verify with proof-rolling.
If the pipe "walks" during backfill, it's either too heavy or you're not using enough hands—call me, I've done both.
Quality Assurance, Inspection & Maintenance
1
Initial Inspection Checklist
  • Verify invert elevation at each end and at 50-foot stations
  • Check joint alignment and sealing for watertightness
  • Confirm bedding compaction meets 95% standard
  • Document material certifications and batch test results
2
Routine Maintenance Schedule
  • Remove debris minimum annually before rainy season
  • Inspect riprap condition after significant flow events
  • Check joint seal integrity every 5 years
  • Document all maintenance activities in KDOT database
3
Rehabilitation Triggers
  • Pipe deformation exceeding 2% of diameter
  • Significant joint separation or displacement
  • Evidence of soil infiltration or piping
  • Structural cracking or spalling in concrete elements
Performance Evaluation Metrics
Regular culvert assessment ensures early identification of potential failures. Document these key performance indicators:
Safety, Documentation & Regulatory Compliance
Public Safety Measures
Safety is non-negotiable at every stage of culvert projects. Implement these critical safeguards:
  • MUTCD-compliant temporary traffic control with proper detours or flagging
  • OSHA-mandated shoring plans for trenches deeper than 5 feet (§1926.652)
  • Confined space entry procedures for culvert maintenance
  • Public notification for road closures at least 7 days in advance
Essential Documentation
As-Built Drawings
Record final invert elevations, stationing, material specifications, and any field modifications from original design.
Inspection Logs
Compile all QA/QC reports, material certificates, compaction tests, and photographic documentation.
Maintenance Manual
Provide "Day 1" pocket folder with maintenance checklists, emergency contacts, and inspection schedules.
If a future engineer can't find your as-builts, they'll assume you never built it—and that can cost you your retirement party.
Upload all documentation to the KDOT OnBase system with appropriate QA track number references. Maintain copies of all environmental permits (Stream Crossing, 404/401 Water Quality) with project files for future regulatory inspections.